The AI Compute Race Campuses Campus 8 of 40

Stargate Shackelford / Frontier (Vantage Data Centers; Oracle; OpenAI tenant), Shackelford County, Texas, US

Vantage Data Centers; Oracle; OpenAI tenant

Stargate Shackelford / Frontier (Vantage Data Centers, Oracle and OpenAI tenant; Shackelford County, Texas, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,400 MW announced or estimated. The book’s verdict: not yet due.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)1,400 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictNot yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Not yet due.
  • Evidence read
  • Today
  • Promised

0 MW evidenced at the end-of-August 2026 reading, of 1,400 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
1,400 MW
Where the announcement was read
vantage-dc.com
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
vantage-dc.com

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
epoch.ai
When it was read
The book’s verdict
Not yet due

The book’s note

First building promised for H2 2026 (August 2026 compilation’s table of promised dates row 33; the August 2026 compilation). Epoch estimates the first building at about 15 Aug 2027. 1,400 MW is Vantage’s critical-IT figure.

Also

Who is involved

The dated tests that name it

Campuses near it in the ledger

Questions about this campus

Is Stargate Shackelford / Frontier energized?
Stargate Shackelford / Frontier (Vantage Data Centers, Oracle and OpenAI tenant; Shackelford County, Texas, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,400 MW announced or estimated. The book’s verdict: not yet due.
When was Stargate Shackelford / Frontier promised to be energized?
Stargate Shackelford / Frontier was promised operations by 31 December 2026.
Who is building Stargate Shackelford / Frontier?
Vantage Data Centers (developer), Oracle (operator), OpenAI (tenant).
How to cite this page

Dryburgh, Lee S. “Stargate Shackelford / Frontier.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-shackelford-frontier (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-shackelford-frontier-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Shackelford / Frontier}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-shackelford-frontier},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON