Project Matador / HyperGrid (Fermi America; TensorWave first tenant), Amarillo (Carson County), Texas, US

Fermi America; TensorWave first tenant

Project Matador / HyperGrid (Fermi America and TensorWave first tenant; Amarillo (Carson County), Texas, US) was promised first power by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load. The book’s verdict: not yet due.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)not on file
Evidenced power (IT load), end of August 20260 MW
The book’s verdictNot yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Not yet due.
  • Evidence read
  • Today
  • Promised

The announcement

Announced or estimated capacity (IT load)
not on file
Where the announcement was read
sec.gov
When it was read

The promise

Promised by
What was promised
first power
Where the promise was read
sec.gov

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
sec.gov
When it was read
The book’s verdict
Not yet due

The book’s note

17,000 MW is a private-power plan, not IT; the first tenant is 222 MW of facility load, due H2 2027. First power in 2026 (the August 2026 compilation; the August 2026 compilation’s table of promised dates, row 1, has 86 MW of grid service in H2 2026). An IT figure would need Fermi’s own critical-load statement. Fermi’s 10-Q of 14 August 2026 gives the lease’s target delivery dates, the end of 2027 to 1 February 2028, and its closing condition, project financing by 30 September 2026. After the close: the fact sheet Fermi furnished to the SEC on 14 October 2026 (Exhibit 99.1 to its Form 8-K) gives 156 MW critical IT capacity of 222 MW total power for the first tenant’s phase alone, delivery from late 2027; the announced cell keeps its state at the close. Fermi’s own filings had moved the promise before the close: the IPO prospectus of 1 October 2025 said the company intended to “deploy at least 1.1 GW of power by the end of 2026” with “a target date to commence operations of March 2026”; the 10-K of 30 March 2026 said “86 MW expected to be energized in the second half of 2026” and Phase 1 “substantially completed upon initial tenant energization and commissioning readiness” expected “during the first half of 2027”.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Project Matador / HyperGrid energized?
Project Matador / HyperGrid (Fermi America and TensorWave first tenant; Amarillo (Carson County), Texas, US) was promised first power by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load. The book’s verdict: not yet due.
When was Project Matador / HyperGrid promised to be energized?
Project Matador / HyperGrid was promised first power by 31 December 2026.
Who is building Project Matador / HyperGrid?
Fermi America (developer), TensorWave (tenant).
How to cite this page

Dryburgh, Lee S. “Project Matador / HyperGrid.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/project-matador-hypergrid (accessed 2026-11-01).

BibTeX

@misc{dryburgh-project-matador-hypergrid-2026,
  author = {Dryburgh, Lee S.},
  title = {{Project Matador / HyperGrid}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/project-matador-hypergrid},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON