Helios (Galaxy Digital and CoreWeave tenant; Dickens County, Texas, US) was promised operations by 30 June 2026; at the end-of-August 2026 reading the public record evidences 133 MW of IT load against 526 MW announced or estimated. The book’s verdict: slipped.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)526 MW
Evidenced power (IT load), end of August 2026133 MW
The book’s verdictSlipped

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Slipped.
  • Promised
  • Evidence read
  • Today

133 MW evidenced at the end-of-August 2026 reading, of 526 MW announced or estimated (25%).

The announcement

Announced or estimated capacity (IT load)
526 MW
Where the announcement was read
prnewswire.com
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
galaxy.com

At the close of the record

Evidenced power (IT load), end of August 2026
133 MW
Where the evidence was read
prnewswire.com
When it was read
The book’s verdict
Slipped

The book’s note

The August 2026 compilation: phase 1 promised for H1 2026, delivered 6 Jul 2026 (133 MW of critical IT), six days past the half-year. The August 2026 compilation cites Galaxy’s releases of 15 Aug 2025 and 6 Jul 2026 for the row and does not say which states the H1 2026 date; a held copy of the 2025 release would settle it. 526 MW is Galaxy’s contracted critical IT.

Also

Who is involved

Campuses near it in the ledger

Questions about this campus

Is Helios energized?
Helios (Galaxy Digital and CoreWeave tenant; Dickens County, Texas, US) was promised operations by 30 June 2026; at the end-of-August 2026 reading the public record evidences 133 MW of IT load against 526 MW announced or estimated. The book’s verdict: slipped.
When was Helios promised to be energized?
Helios was promised operations by 30 June 2026.
Who is building Helios?
Galaxy Digital (owner), CoreWeave (tenant).
How to cite this page

Dryburgh, Lee S. “Helios.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/helios (accessed 2026-11-01).

BibTeX

@misc{dryburgh-helios-2026,
  author = {Dryburgh, Lee S.},
  title = {{Helios}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/helios},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON