The AI Compute Race Campuses Campus 17 of 40

Stargate Abilene (Crusoe; Oracle; OpenAI), Abilene, Texas, US

Crusoe (with an asset SPV); Oracle; OpenAI

Stargate Abilene (Crusoe, Oracle and OpenAI; Abilene, Texas, US) was promised first power by 30 June 2025; at the end-of-August 2026 reading the public record evidences 421 MW of IT load against 843 MW announced or estimated. The book’s verdict: slipped.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)843 MW
Evidenced power (IT load), end of August 2026421 MW
The book’s verdictSlipped

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Slipped.
  • Promised
  • Evidence read
  • Today

421 MW evidenced at the end-of-August 2026 reading, of 843 MW announced or estimated (50%).

The announcement

Announced or estimated capacity (IT load)
843 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
first power
Where the promise was read
crusoe.ai

At the close of the record

Evidenced power (IT load), end of August 2026
421 MW
Where the evidence was read
epoch.ai
When it was read
The book’s verdict
Slipped

The book’s note

The two-building, 200+ MW first phase ‘expected to be energized in the first half of 2025’ (Crusoe, 18 Mar 2025; the August 2026 compilation’s table of promised dates dates the same promise to Crusoe and Lancium, 21 Apr 2024). Epoch dates 211 MW to 24 Dec 2025, about six months late; Crusoe has the phase live 30 Sep 2025. Chapter 12’s anchor, outside the August 2026 compilation’s table of promised dates’s forty but row 17 of this ledger. 843 MW is Epoch’s estimate.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Stargate Abilene energized?
Stargate Abilene (Crusoe, Oracle and OpenAI; Abilene, Texas, US) was promised first power by 30 June 2025; at the end-of-August 2026 reading the public record evidences 421 MW of IT load against 843 MW announced or estimated. The book’s verdict: slipped.
When was Stargate Abilene promised to be energized?
Stargate Abilene was promised first power by 30 June 2025.
Who is building Stargate Abilene?
Crusoe (developer), Crusoe asset SPV (owner), Oracle (operator), OpenAI (tenant).
How to cite this page

Dryburgh, Lee S. “Stargate Abilene.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-abilene (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-abilene-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Abilene}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-abilene},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON