Stargate Milam County (SB Energy, SoftBank and OpenAI tenant; Milam County, Texas, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 857 MW announced or estimated. The book’s verdict: not yet due.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)857 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictNot yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Not yet due.
  • Evidence read
  • Today
  • Promised

0 MW evidenced at the end-of-August 2026 reading, of 857 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
857 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
openai.com

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
sec.gov
When it was read
The book’s verdict
Not yet due

The book’s note

OpenAI’s announcement of 23 Sep 2025 contemplated initial facilities in 2026; a later schedule moved the first 300 MW to 2027 (August 2026 compilation’s table of promised dates row 38, revised before maturity). SB Energy’s S-1 and its amendment of 21 Sep 2026 give ‘Phase 1-A (200 MW … targeted August 2026)’; on that target the clock would have matured, and no energization of it is held. 857 MW is Epoch’s estimate.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Stargate Milam County energized?
Stargate Milam County (SB Energy, SoftBank and OpenAI tenant; Milam County, Texas, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 857 MW announced or estimated. The book’s verdict: not yet due.
When was Stargate Milam County promised to be energized?
Stargate Milam County was promised operations by 31 December 2026.
Who is building Stargate Milam County?
SB Energy (owner), SoftBank (partner), OpenAI (tenant).
How to cite this page

Dryburgh, Lee S. “Stargate Milam County.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-milam-county (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-milam-county-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Milam County}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-milam-county},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON