Stargate Port Washington / Lighthouse (Vantage Data Centers; Oracle; OpenAI), Port Washington, Wisconsin, US

Vantage Data Centers; Oracle; OpenAI

Stargate Port Washington / Lighthouse (Vantage Data Centers, Oracle and OpenAI; Port Washington, Wisconsin, US) was promised operations by 31 December 2028; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 902 MW announced or estimated. The book’s verdict: not yet due.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)902 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictNot yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Not yet due.
  • Evidence read
  • Today
  • Promised

0 MW evidenced at the end-of-August 2026 reading, of 902 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
902 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
vantage-dc.com

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
not on file
When it was read
The book’s verdict
Not yet due

The book’s note

Completion scheduled for 2028 (August 2026 compilation’s table of promised dates row 39; the August 2026 compilation beside Vantage’s announcement). 902 MW is Epoch’s estimate. The August 2026 compilation records 0 publicly verified and names no source for the zero.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Stargate Port Washington / Lighthouse energized?
Stargate Port Washington / Lighthouse (Vantage Data Centers, Oracle and OpenAI; Port Washington, Wisconsin, US) was promised operations by 31 December 2028; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 902 MW announced or estimated. The book’s verdict: not yet due.
When was Stargate Port Washington / Lighthouse promised to be energized?
Stargate Port Washington / Lighthouse was promised operations by 31 December 2028.
Who is building Stargate Port Washington / Lighthouse?
Vantage Data Centers (developer), Oracle (operator), OpenAI (tenant).
How to cite this page

Dryburgh, Lee S. “Stargate Port Washington / Lighthouse.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-port-washington-lighthouse (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-port-washington-lighthouse-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Port Washington / Lighthouse}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-port-washington-lighthouse},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON