The AI Compute Race Campuses Campus 4 of 40

Fairwater Wisconsin (Microsoft), Mount Pleasant, Wisconsin, US

Microsoft

Fairwater Wisconsin (Microsoft; Mount Pleasant, Wisconsin, US) was promised operations by 31 March 2026; at the end-of-August 2026 reading the public record evidences 369 MW of IT load against 2,263 MW announced or estimated. The book’s verdict: missed, if ‘early 2026’ meant the first quarter (the book counts it as a miss).

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)2,263 MW
Evidenced power (IT load), end of August 2026369 MW
The book’s verdictMissed, if ‘early 2026’ meant the first quarter (the book counts it as a miss)

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Missed, if ‘early 2026’ meant the first quarter (the book counts it as a miss).
  • Promised
  • Evidence read
  • Today

369 MW evidenced at the end-of-August 2026 reading, of 2,263 MW announced or estimated (16%).

The announcement

Announced or estimated capacity (IT load)
2,263 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
blogs.microsoft.com

At the close of the record

Evidenced power (IT load), end of August 2026
369 MW
Where the evidence was read
epoch.ai
When it was read
The book’s verdict
Missed, if ‘early 2026’ meant the first quarter (the book counts it as a miss)

The book’s note

Promised ‘online in early 2026’ (18 Sep 2025), read as 31 March. Epoch dates the first building operating on 16 April 2026, 16 days late on that reading; Microsoft’s chief executive called it six weeks ahead of schedule. 2,263 MW is Epoch’s estimate, not Microsoft’s figure. Slippage matrix row 21. Status word aligned with the book’s August 2026 compilation’s table of promised dates at rev 589 (6 Oct 2026): missed if ‘early 2026’ means the first quarter; called six weeks early by its chief executive.

Also

Who is involved

Campuses near it in the ledger

Questions about this campus

Is Fairwater Wisconsin energized?
Fairwater Wisconsin (Microsoft; Mount Pleasant, Wisconsin, US) was promised operations by 31 March 2026; at the end-of-August 2026 reading the public record evidences 369 MW of IT load against 2,263 MW announced or estimated. The book’s verdict: missed, if ‘early 2026’ meant the first quarter (the book counts it as a miss).
When was Fairwater Wisconsin promised to be energized?
Fairwater Wisconsin was promised operations by 31 March 2026.
Who is building Fairwater Wisconsin?
Microsoft (owner).
How to cite this page

Dryburgh, Lee S. “Fairwater Wisconsin.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/fairwater-wisconsin (accessed 2026-11-01).

BibTeX

@misc{dryburgh-fairwater-wisconsin-2026,
  author = {Dryburgh, Lee S.},
  title = {{Fairwater Wisconsin}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/fairwater-wisconsin},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON