The AI Compute Race Campuses Campus 23 of 40

Stargate Norway (Nscale–Aker joint venture; OpenAI offtaker), Kvandal, Narvik, Norway

Nscale–Aker joint venture; OpenAI offtaker (Microsoft from April 2026)

Stargate Norway (Nscale–Aker joint venture and OpenAI offtaker; Kvandal, Narvik, Norway) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 230 MW announced or estimated. The book’s verdict: transferred.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)230 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictTransferred

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Transferred.
  • Evidence read
  • Today
  • Promised

0 MW evidenced at the end-of-August 2026 reading, of 230 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
230 MW
Where the announcement was read
openai.com
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
openai.com

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
cnbc.com
When it was read
The book’s verdict
Transferred

The book’s note

100,000 NVIDIA GPUs targeted by the end of 2026. On 15 Apr 2026 Microsoft took the compute earmarked for OpenAI; the August 2026 compilation’s table of promised dates (anchor addendum) records it retreated and transferred, with no clock across two projects. Chapter 12’s transferred project is a different one, Tembo/Jade in Wyoming.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Stargate Norway energized?
Stargate Norway (Nscale–Aker joint venture and OpenAI offtaker; Kvandal, Narvik, Norway) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 230 MW announced or estimated. The book’s verdict: transferred.
When was Stargate Norway promised to be energized?
Stargate Norway was promised operations by 31 December 2026.
Who is building Stargate Norway?
Nscale–Aker joint venture (owner), OpenAI (offtaker), Microsoft (offtaker).
How to cite this page

Dryburgh, Lee S. “Stargate Norway.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-norway (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-norway-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Norway}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-norway},
  note = {Accessed 2026-11-01}
}