The AI Compute Race Campuses Campus 22 of 40

Colossus 1 (xAI; Anthropic contracted all capacity), Memphis, Tennessee, US

xAI (SpaceXAI); Anthropic contracted all capacity

Colossus 1 (xAI and Anthropic contracted all capacity; Memphis, Tennessee, US) was promised training start by 31 July 2024; at the end-of-August 2026 reading the public record evidences 340 MW of IT load against 340 MW announced or estimated. The book’s verdict: kept.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)340 MW
Evidenced power (IT load), end of August 2026340 MW
The book’s verdictKept

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Kept.
  • Promised
  • Evidence read
  • Today

340 MW evidenced at the end-of-August 2026 reading, of 340 MW announced or estimated (100%).

The announcement

Announced or estimated capacity (IT load)
340 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
training start
Where the promise was read
x.com

At the close of the record

Evidenced power (IT load), end of August 2026
340 MW
Where the evidence was read
epoch.ai
When it was read
The book’s verdict
Kept

The book’s note

Dated before launch by the builder’s own word: Musk on X, 9 July 2024, ‘Aiming to begin training later this month’; training began 22 July 2024 (chapter 4). Earlier note read ‘No pre-launch, checkable first-power date; the 122 days was published after the fact’, which overlooked the post; changed 25 October 2026. 340 MW is Epoch’s current estimate. The promise is the principal’s own post of 9 July 2024, a target: ‘Aiming to begin training later this month’.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Colossus 1 energized?
Colossus 1 (xAI and Anthropic contracted all capacity; Memphis, Tennessee, US) was promised training start by 31 July 2024; at the end-of-August 2026 reading the public record evidences 340 MW of IT load against 340 MW announced or estimated. The book’s verdict: kept.
When was Colossus 1 promised to be energized?
Colossus 1 was promised training start by 31 July 2024.
Who is building Colossus 1?
xAI (SpaceXAI) (owner), Anthropic (offtaker).
How to cite this page

Dryburgh, Lee S. “Colossus 1.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/colossus-1 (accessed 2026-11-01).

BibTeX

@misc{dryburgh-colossus-1-2026,
  author = {Dryburgh, Lee S.},
  title = {{Colossus 1}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/colossus-1},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON