Stargate Doña Ana / Project Jupiter (Oracle-led facility; OpenAI tenant), Doña Ana County, New Mexico, US

Oracle-led facility (Stack Infrastructure, Blue Owl, developer); OpenAI tenant

Stargate Doña Ana / Project Jupiter (Oracle-led facility and OpenAI tenant; Doña Ana County, New Mexico, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,750 MW announced or estimated. The book’s verdict: not yet due.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)1,750 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictNot yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Not yet due.
  • Evidence read
  • Today
  • Promised

0 MW evidenced at the end-of-August 2026 reading, of 1,750 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
1,750 MW
Where the announcement was read
epoch.ai
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
not on file

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
epoch.ai
When it was read
The book’s verdict
Not yet due

The book’s note

Initial operations in Q4 2026 per the August 2026 compilation’s table of promised dates (row 19), which gives no URL; the August 2026 compilation’s ‘December 2027’ is a stormwater-permit period, not a customer promise. Oracle asserted force majeure rights on 24 Sep 2026 and said Project Jupiter ‘remains on our planned schedule’. 1,750 MW is Epoch’s estimate from the fuel-cell microgrid.

Also

Who is involved

Filings that bear on it

Campuses near it in the ledger

Questions about this campus

Is Stargate Doña Ana / Project Jupiter energized?
Stargate Doña Ana / Project Jupiter (Oracle-led facility and OpenAI tenant; Doña Ana County, New Mexico, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,750 MW announced or estimated. The book’s verdict: not yet due.
When was Stargate Doña Ana / Project Jupiter promised to be energized?
Stargate Doña Ana / Project Jupiter was promised operations by 31 December 2026.
Who is building Stargate Doña Ana / Project Jupiter?
Oracle (operator), Stack Infrastructure (developer), Blue Owl (financier), OpenAI (tenant).
How to cite this page

Dryburgh, Lee S. “Stargate Doña Ana / Project Jupiter.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/stargate-dona-ana-project-jupiter (accessed 2026-11-01).

BibTeX

@misc{dryburgh-stargate-don-a-ana-project-jupiter-2026,
  author = {Dryburgh, Lee S.},
  title = {{Stargate Doña Ana / Project Jupiter}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/stargate-dona-ana-project-jupiter},
  note = {Accessed 2026-11-01}
}