The AI Compute Race Campuses Campus 3 of 40

Scala AI City (Scala Data Centers), Eldorado do Sul, Rio Grande do Sul, Brazil

Scala Data Centers (DigitalBridge)

Scala AI City (Scala Data Centers; Eldorado do Sul, Rio Grande do Sul, Brazil) was promised operations by 11 September 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 4,750 MW announced or estimated. The book’s verdict: missed.

From The AI Compute Race. Read the book

Download this campus: CSV · JSON

Announced or estimated (IT load)4,750 MW
Evidenced power (IT load), end of August 20260 MW
The book’s verdictMissed

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: Missed.
  • Promised
  • Evidence read
  • Today

0 MW evidenced at the end-of-August 2026 reading, of 4,750 MW announced or estimated (0%).

The announcement

Announced or estimated capacity (IT load)
4,750 MW
Where the announcement was read
scaladatacenters.com
When it was read

The promise

Promised by
What was promised
operations
Where the promise was read
teletime.com.br

At the close of the record

Evidenced power (IT load), end of August 2026
0 MW
Where the evidence was read
investmentmonitor.ai
When it was read
The book’s verdict
Missed

The book’s note

4,750 MW is the end-state; the promise is the first 54 MW within two years of 11 Sep 2024. No energization found in a search to the close (close sweep, ch11 §8); in April 2026 construction of the first phase was put toward the end of 2026. Chapter 12 scores it missed. Slippage matrix row 11. Status word aligned with the book’s August 2026 compilation’s table of promised dates at rev 589 (6 Oct 2026): the first 54 MW of IT capacity, due 11 September 2026, missed.

Also

Who is involved

Questions about this campus

Is Scala AI City energized?
Scala AI City (Scala Data Centers; Eldorado do Sul, Rio Grande do Sul, Brazil) was promised operations by 11 September 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 4,750 MW announced or estimated. The book’s verdict: missed.
When was Scala AI City promised to be energized?
Scala AI City was promised operations by 11 September 2026.
Who is building Scala AI City?
Scala Data Centers (developer), DigitalBridge (owner).
How to cite this page

Dryburgh, Lee S. “Scala AI City.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/ledger/scala-ai-city (accessed 2026-11-01).

BibTeX

@misc{dryburgh-scala-ai-city-2026,
  author = {Dryburgh, Lee S.},
  title = {{Scala AI City}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/ledger/scala-ai-city},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON