The AI Compute Race Campuses Places Wisconsin, US

Wisconsin, US

2 of the forty campuses in the ledger

Two of the forty campuses in the ledger are in Wisconsin. Two of them carry an announced or estimated capacity, 3,165 MW in all. The record evidences 369 MW across the two, at the end-of-August 2026 reading.

1 missed, if ‘early 2026’ meant the first quarter (the book counts it as a miss) · 1 not yet due

From The AI Compute Race. Read the book

The campuses

CampusWhereAnnounced or estimated capacity (IT load)Evidenced power (IT load)The book’s verdict
Fairwater WisconsinMount Pleasant, Wisconsin, US2,263 MW369 MWMissed, if ‘early 2026’ meant the first quarter (the book counts it as a miss)
Stargate Port Washington / LighthousePort Washington, Wisconsin, US902 MW0 MWNot yet due

Who is involved

Every figure is the campus page’s own, read at the end of August 2026; each campus page carries its sources. Places · All 40 campuses.