Four of the forty campuses in the ledger are in Ohio. Four of them carry an announced or estimated capacity, 9,521 MW in all. The record evidences 1,015 MW across the four, at the end-of-August 2026 reading.
2 not yet due · 1 kept · 1 never dated
From The AI Compute Race. Read the book
The campuses
| Campus | Where | Announced or estimated capacity (IT load) | Evidenced power (IT load) | The book’s verdict |
|---|---|---|---|---|
| PORTS-Pike | Pike County, Ohio, US | 8,000 MW | 0 MW | Not yet due |
| Prometheus | New Albany, Ohio, US | 854 MW | 562 MW | Kept |
| Google New Albany | New Albany, Ohio, US | 453 MW | 453 MW | Never dated |
| Stargate Lordstown | Lordstown, Ohio, US | 214 MW | 0 MW | Not yet due |
Who is involved
Every figure is the campus page’s own, read at the end of August 2026; each campus page carries its sources. Places · All 40 campuses.