The AI Compute Race Tests Chapter 6, deliverability and firmness bind

Chapter 6, deliverability and firmness bind

Due

The test. The claim stands if either Franklin Farms unit slips past the 1 June 2029 rent date. Waterford 5’s own schedule already sits after it.

open Open. Franklin Farms 1 and 2 are dated for service in 2028, and Meta’s rent on the campus’s buildings starts on 1 June 2029.

From The AI Compute Race. Read the book

Falls due
Read on
The U-37425 quarterly monitors
Chapter
Chapter 6 — Firm, Around-the-Clock

Where the electricity comes from: grid queues, transformers, turbines and the firm power a datacenter needs every hour of the year, on calendars the buildout does not control.

What it names

Filings that bear on it

  • Louisiana Public Service Commission, Order in Docket U-37425, 29 August 2025

    Louisiana’s utility commission approved a settlement letting Entergy Louisiana build three combined-cycle generators and transmission for Meta’s Richland Parish data center, with conditions on the customer’s minimum monthly charges, parent guaranty and early termination fee, and quarterly progress reports.

Add this test to your calendar · Download this test: CSV · JSON

How to cite this page

Dryburgh, Lee S. “Chapter 6, deliverability and firmness bind.” In The AI Compute Race. DRYBURGH. https://dryburgh.com/vol1/tests/2029-2 (accessed 2026-11-01).

BibTeX

@misc{dryburgh-chapter-6-deliverability-and-firmness-bi-2026,
  author = {Dryburgh, Lee S.},
  title = {{Chapter 6, deliverability and firmness bind}},
  howpublished = {In \emph{The AI Compute Race}, DRYBURGH},
  year = {2026},
  url = {https://dryburgh.com/vol1/tests/2029-2},
  note = {Accessed 2026-11-01}
}

For a reference manager: RIS · CSL-JSON