Two of the forty campuses in the ledger are in Indiana. One of them carries an announced or estimated capacity, 1,925 MW, and one announces no figure. The record evidences 910 MW across the two, at the end-of-August 2026 reading.
1 never dated · 1 not yet due
From The AI Compute Race. Read the book
The campuses
| Campus | Where | Announced or estimated capacity (IT load) | Evidenced power (IT load) | The book’s verdict |
|---|---|---|---|---|
| Rainier / New Carlisle | New Carlisle, Indiana, US | 1,925 MW | 910 MW | Never dated |
| AWS Northern Indiana program | Northern Indiana, US | not on file | 0 MW | Not yet due |
Who is involved
- Amazon AWS 2 of 2
- Anthropic 1 of 2
Every figure is the campus page’s own, read at the end of August 2026; each campus page carries its sources. Places · All 40 campuses.