title: "Stargate Doña Ana / Project Jupiter (Oracle-led facility; OpenAI tenant), Doña Ana County, New Mexico, US — campus ledger — The AI Compute Race — DRYBURGH · The Compute Economy"
source: https://dryburgh.com/vol1/ledger/stargate-dona-ana-project-jupiter
description: "Stargate Doña Ana / Project Jupiter: not yet due. 0 MW evidenced of 1,750 MW announced or estimated, end of August 2026 reading; operations promised by 31…"
---

# Stargate Doña Ana / Project Jupiter (Oracle-led facility; OpenAI tenant), Doña Ana County, New Mexico, US

Oracle-led facility (Stack Infrastructure, Blue Owl, developer); OpenAI tenant

Stargate Doña Ana / Project Jupiter (Oracle-led facility and OpenAI tenant; Doña Ana County, New Mexico, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,750 MW announced or estimated. The book’s verdict: not yet due.

From *The AI Compute Race*. [Read the book](https://dryburgh.com/vol1#buy)

Download this campus: [CSV](https://dryburgh.com/vol1/data/ledger-stargate-dona-ana-project-jupiter.csv) · [JSON](https://dryburgh.com/vol1/data/ledger-stargate-dona-ana-project-jupiter.json)

Announced or estimated (IT load) 1,750 MW

Evidenced power (IT load), end of August 2026 0 MW

The book’s verdict Not yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: **Not yet due**.

- Evidence read 28 August 2026
- Today Nov 2026
- Promised 31 December 2026

**0 MW** evidenced at the end-of-August 2026 reading, of 1,750 MW announced or estimated (0%).

## The announcement

**Announced or estimated capacity (IT load):** 1,750 MW

**Where the announcement was read:** [epoch.ai](https://epoch.ai/data/ai-data-centers/directory/openai-stargate-new-mexico)

**When it was read:** 28 August 2026

## The promise

**Promised by:** 31 December 2026

**What was promised:** operations

**Where the promise was read:** not on file

## At the close of the record

**Evidenced power (IT load), end of August 2026:** 0 MW

**Where the evidence was read:** [epoch.ai](https://epoch.ai/data/ai-data-centers/directory/openai-stargate-new-mexico)

**When it was read:** 28 August 2026

**The book’s verdict:** Not yet due

## The book’s note

Initial operations in Q4 2026 per the August 2026 compilation’s table of promised dates (row 19), which gives no URL; the August 2026 compilation’s ‘December 2027’ is a stormwater-permit period, not a customer promise. Oracle asserted force majeure rights on 24 Sep 2026 and said Project Jupiter ‘remains on our planned schedule’. 1,750 MW is Epoch’s estimate from the fuel-cell microgrid.

## Also

**Who is involved:**

- operator [Oracle](https://dryburgh.com/vol1/parties/oracle)
- developer [Stack Infrastructure](https://dryburgh.com/vol1/parties/stack-infrastructure)
- financier [Blue Owl](https://dryburgh.com/vol1/parties/blue-owl)
- tenant [OpenAI](https://dryburgh.com/vol1/parties/openai)

## Filings that bear on it

- [Yucca Growth Infrastructure, LLC and Oracle America Cloud Services LLC, “Project Jupiter 2026 Consolidated Annual Report,” to the County Manager of Doña Ana County under Section 4.21 of the bonds’ leases, 31 July 2026, signed by Leslie Mitchell, Director, Tax Planning, Oracle](https://dryburgh.com/vol1/filings/jupiter-annual-report-jul26) Oracle and Yucca Growth told Doña Ana County on 31 July 2026 that Project Jupiter’s microgrid was about 10 percent and its data center about 9 percent complete at 30 June, with the 775 required jobs not yet hired.
- [Federal Energy Regulatory Commission, Docket No. CP26-80-000, Transwestern Pipeline Company, LLC, Green Chile Project](https://dryburgh.com/vol1/filings/ferc-greenchile-2026) FERC’s notice describes Transwestern’s Green Chile Project, about 17.8 miles of pipeline in Doña Ana County for an AI data center campus’s power, and Transwestern later moved its estimated in-service date from 15 August 2026 to 1 February 2027.
- [Oracle Corporation, “Renewed Request of Oracle Corporation for Expedited Issuance of Authorization,” FERC Docket No. CP26-80-000](https://dryburgh.com/vol1/filings/oracle-ferc-cp26-80-oct26) Oracle renewed on 13 October 2026 its request that FERC expedite approval of the Green Chile pipeline, saying no procedural steps remain and that delay “threatens to delay Project Jupiter’s operations.”
- [STACK Infrastructure, comments in support of the Green Chile Project, FERC Docket No. CP26-80-000, dated 12 October 2026 and filed 13 October 2026, accession 20261013-5329](https://dryburgh.com/vol1/filings/stack-ferc-cp26-80-oct26) STACK Infrastructure asked FERC on 12 October 2026 to authorize the Green Chile pipeline for Project Jupiter quickly, saying more than 1,200 New Mexico residents worked on the campus at 30 September and delays would raise costs.
- [Transwestern Pipeline Company, LLC, “Response to Comments on the Environmental Assessment,” FERC Docket No. CP26-80-000](https://dryburgh.com/vol1/filings/transwestern-ferc-cp26-80-oct26) Transwestern told FERC on 12 October 2026 that its agreement with Green Chile Ventures for all the pipeline’s capacity is “still in full force and effect” and that the shipper cannot terminate over the past-due target dates.
- [Doña Ana County Board of County Commissioners, agenda packet for the regular meeting of 19 September 2025, published on the county’s CivicClerk portal on 15 September 2025](https://dryburgh.com/vol1/filings/donaana-bocc-packet-sep25) Doña Ana County’s packet for the 19 September 2025 meeting carries the Project Jupiter bond ordinance, up to $165 billion, and an unsigned understanding paying the county $12 million a year in lieu of taxes for thirty years.
- [Project Jupiter Community Benefits Agreement among Red Chiles A, B, C and D, LLC, Yucca Growth Infrastructure, LLC and Doña Ana County, New Mexico, made and executed on 12 November 2025](https://dryburgh.com/vol1/filings/donaana-jupiter-cba-nov25) Project Jupiter’s community benefits agreement of 12 November 2025 schedules payments to Doña Ana County, $4 million of them for workforce education, puts average water use at 20,000 gallons a day, and gives the county no separate damages claim.
- [Doña Ana County Board of County Commissioners, “A Resolution Relating to the Proposed Industrial Revenue Bonds, Entitled Doña Ana County, New Mexico Taxable Industrial Revenue Bonds, Project Jupiter; Declaring the Intent of Doña Ana County to Issue Such Industrial Revenue Bonds in an Aggregate Principal Amount up to $165,000,000,000,” inducement resolution with its notice of intent, agenda item 17 of the regular meeting of 26 August 2025, pages 553 to 572 of the meeting’s agenda packet](https://dryburgh.com/vol1/filings/donaana-jupiter-inducement-aug25) The inducement resolution put to Doña Ana County’s commission on 26 August 2025 declares intent to issue up to $165 billion of bonds for Project Jupiter, not county debt and sold only to the companies’ affiliates or parent.
- [Doña Ana County, New Mexico, Taxable Industrial Revenue Bonds, Project Jupiter, Series 2025A, 2025B and 2025C, the lease agreements and the bond purchase agreements, executed and recorded on 12 November 2025](https://dryburgh.com/vol1/filings/donaana-jupiter-irb-nov25) Doña Ana County’s recorded Project Jupiter bond documents of 12 November 2025 have Oracle America buy up to about $125 billion of Series 2025C bonds and chart thirty yearly payments in lieu of taxes from 2026 to 2055.
- [Doña Ana County Board of County Commissioners, Ordinance No. 368-2025, adopted 19 September 2025, and the Project Participation Agreement among Doña Ana County, the New Mexico Economic Development Department, Red Chiles A, B, C and D, LLC and Yucca Growth Infrastructure, LLC, effective 23 October 2025, under the Local Economic Development Act](https://dryburgh.com/vol1/filings/donaana-jupiter-leda-oct25) Under Doña Ana County’s Ordinance 368-2025 and an agreement effective 23 October 2025, half the county’s tax increment from Project Jupiter’s construction goes to the project for ten years, its first $50 million returned for southern county water works.
- [Doña Ana County and Project Jupiter, “Memorandum of Understanding by and between Doña Ana County, New Mexico and Project Jupiter, by and through its affiliated development entities,” signed for the county on 22 September 2025 and for Project Jupiter on 24 September 2025](https://dryburgh.com/vol1/filings/donaana-jupiter-mou-sep25) Doña Ana County and Project Jupiter’s memorandum, signed on 22 and 24 September 2025, grants a full 30-year property tax abatement against payments in lieu of taxes of $12 million a year, $360 million in all.
- [Raúl Torrez, Attorney General of New Mexico, for the State of New Mexico, Response of the Attorney General in Support of Petitioner’s Emergency Verified Petition for Writ of Mandamus and Request for Stay, Center for Biological Diversity v. Elizabeth Anderson, State Engineer, Supreme Court of New Mexico No. S-1-SC-41580, 2 September 2026](https://dryburgh.com/vol1/filings/nmdoj-cbd-anderson-sep26) New Mexico’s attorney general told its Supreme Court on 2 September 2026 that delay in building a private data center is not a genuine emergency, and urged it to bar groundwater use for Project Jupiter’s construction until a hearing.

## Campuses near it in the ledger

- [Stargate Shackelford / Frontier](https://dryburgh.com/vol1/ledger/stargate-shackelford-frontier) shares 2 parties
- [Stargate UAE](https://dryburgh.com/vol1/ledger/stargate-uae) shares 2 parties
- [Stargate Michigan / The Barn](https://dryburgh.com/vol1/ledger/stargate-michigan-the-barn) shares 2 parties
- [Stargate Port Washington / Lighthouse](https://dryburgh.com/vol1/ledger/stargate-port-washington-lighthouse) shares 2 parties
- [Stargate Abilene](https://dryburgh.com/vol1/ledger/stargate-abilene) shares 2 parties
- [PORTS-Pike](https://dryburgh.com/vol1/ledger/ports-pike) shares a party

## Questions about this campus

**Is Stargate Doña Ana / Project Jupiter energized?:** Stargate Doña Ana / Project Jupiter (Oracle-led facility and OpenAI tenant; Doña Ana County, New Mexico, US) was promised operations by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load against 1,750 MW announced or estimated. The book’s verdict: not yet due.

**When was Stargate Doña Ana / Project Jupiter promised to be energized?:** Stargate Doña Ana / Project Jupiter was promised operations by 31 December 2026.

**Who is building Stargate Doña Ana / Project Jupiter?:** Oracle (operator), Stack Infrastructure (developer), Blue Owl (financier), OpenAI (tenant).

- [Tests](https://dryburgh.com/vol1/tests)
- [Scorecard](https://dryburgh.com/vol1/scorecard)
- [Data](https://dryburgh.com/vol1/data/releases)
- [Chapter by chapter](https://dryburgh.com/vol1/companion)
- [The record at a glance](https://dryburgh.com/vol1/observatory)
- [The machine](https://dryburgh.com/vol1/machine)
- [One campus, four futures](https://dryburgh.com/vol1/hyperion)
- [Glossary](https://dryburgh.com/vol1/glossary)
- [People](https://dryburgh.com/vol1/people)
- [Sources](https://dryburgh.com/vol1/sources)
- [Notes](https://dryburgh.com/vol1/notes)
- [Where the book was wrong](https://dryburgh.com/vol1/corrections)
- [Where its sources were wrong](https://dryburgh.com/corrections?book=vol1)
- [The Paper](https://dryburgh.com/vol1/paper)
- [Consent](https://dryburgh.com/vol1/consent)
- [Who builds and pays](https://dryburgh.com/vol1/parties)