# Project Matador / HyperGrid (Fermi America; TensorWave first tenant), Amarillo (Carson County), Texas, US

Fermi America; TensorWave first tenant

Project Matador / HyperGrid (Fermi America and TensorWave first tenant; Amarillo (Carson County), Texas, US) was promised first power by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load. The book’s verdict: not yet due.

From *The AI Compute Race*. [Read the book](https://dryburgh.com/vol1#buy)

Download this campus: [CSV](https://dryburgh.com/vol1/data/ledger-project-matador-hypergrid.csv) · [JSON](https://dryburgh.com/vol1/data/ledger-project-matador-hypergrid.json)

Announced or estimated (IT load) not on file

Evidenced power (IT load), end of August 2026 0 MW

The book’s verdict Not yet due

The ledger’s reading is the end of August 2026: the promises and the states as they stood then. Each row’s evidence carries its own date, printed on it.

The promise and the record, on one line. The book’s verdict: **Not yet due**.

- Evidence read 13 August 2026
- Today Nov 2026
- Promised 31 December 2026

## The announcement

**Announced or estimated capacity (IT load):** not on file

**Where the announcement was read:** [sec.gov](https://www.sec.gov/Archives/edgar/data/2071778/000207177826000046/fermi2q2026investorprese.htm)

**When it was read:** 13 August 2026

## The promise

**Promised by:** 31 December 2026

**What was promised:** first power

**Where the promise was read:** [sec.gov](https://www.sec.gov/Archives/edgar/data/2071778/000207177826000046/fermi2q2026investorprese.htm)

## At the close of the record

**Evidenced power (IT load), end of August 2026:** 0 MW

**Where the evidence was read:** [sec.gov](https://www.sec.gov/Archives/edgar/data/2071778/000207177826000046/fermi2q2026investorprese.htm)

**When it was read:** 13 August 2026

**The book’s verdict:** Not yet due

## The book’s note

17,000 MW is a private-power plan, not IT; the first tenant is 222 MW of facility load, due H2 2027. First power in 2026 (the August 2026 compilation; the August 2026 compilation’s table of promised dates, row 1, has 86 MW of grid service in H2 2026). An IT figure would need Fermi’s own critical-load statement. Fermi’s 10-Q of 14 August 2026 gives the lease’s target delivery dates, the end of 2027 to 1 February 2028, and its closing condition, project financing by 30 September 2026. After the close: the fact sheet Fermi furnished to the SEC on 14 October 2026 (Exhibit 99.1 to its Form 8-K) gives 156 MW critical IT capacity of 222 MW total power for the first tenant’s phase alone, delivery from late 2027; the announced cell keeps its state at the close. Fermi’s own filings had moved the promise before the close: the IPO prospectus of 1 October 2025 said the company intended to “deploy at least 1.1 GW of power by the end of 2026” with “a target date to commence operations of March 2026”; the 10-K of 30 March 2026 said “86 MW expected to be energized in the second half of 2026” and Phase 1 “substantially completed upon initial tenant energization and commissioning readiness” expected “during the first half of 2027”.

## Also

**Who is involved:**

- developer [Fermi America](https://dryburgh.com/vol1/parties/fermi-america)
- tenant [TensorWave](https://dryburgh.com/vol1/parties/tensorwave)

## Filings that bear on it

- [Fermi Inc., Form 8-K of 14 October 2026, Exhibit 99.1, “The TensorWave Lease” fact sheet](https://dryburgh.com/vol1/filings/fermi-8k-ex991-tensorwave-oct26) Fermi’s fact sheet of 14 October 2026 describes TensorWave’s binding 15-year phase one lease of 222 megawatts, $6.5 billion of contracted revenue, backed by AMD credit support that begins once construction is complete and rent starts.

## Campuses near it in the ledger

- [Stargate Shackelford / Frontier](https://dryburgh.com/vol1/ledger/stargate-shackelford-frontier) Texas, US
- [Stargate Milam County](https://dryburgh.com/vol1/ledger/stargate-milam-county) Texas, US
- [Stargate Abilene](https://dryburgh.com/vol1/ledger/stargate-abilene) Texas, US
- [Helios](https://dryburgh.com/vol1/ledger/helios) Texas, US

## Questions about this campus

**Is Project Matador / HyperGrid energized?:** Project Matador / HyperGrid (Fermi America and TensorWave first tenant; Amarillo (Carson County), Texas, US) was promised first power by 31 December 2026; at the end-of-August 2026 reading the public record evidences 0 MW of IT load. The book’s verdict: not yet due.

**When was Project Matador / HyperGrid promised to be energized?:** Project Matador / HyperGrid was promised first power by 31 December 2026.

**Who is building Project Matador / HyperGrid?:** Fermi America (developer), TensorWave (tenant).

- [Tests](https://dryburgh.com/vol1/tests)
- [Scorecard](https://dryburgh.com/vol1/scorecard)
- [Data](https://dryburgh.com/vol1/data/releases)
- [Chapter by chapter](https://dryburgh.com/vol1/companion)
- [The record at a glance](https://dryburgh.com/vol1/observatory)
- [The machine](https://dryburgh.com/vol1/machine)
- [One campus, four futures](https://dryburgh.com/vol1/hyperion)
- [Glossary](https://dryburgh.com/vol1/glossary)
- [People](https://dryburgh.com/vol1/people)
- [Sources](https://dryburgh.com/vol1/sources)
- [Notes](https://dryburgh.com/vol1/notes)
- [Where the book was wrong](https://dryburgh.com/vol1/corrections)
- [Where its sources were wrong](https://dryburgh.com/corrections?book=vol1)
- [The Paper](https://dryburgh.com/vol1/paper)
- [Consent](https://dryburgh.com/vol1/consent)
- [Who builds and pays](https://dryburgh.com/vol1/parties)